On July 19th, the Guodian Investment Yangtze River Ecological Hydrogen Production and Storage Project in Keerqin Right Wing Front Banner, Inner Mongolia, and the Green Hydrogen to Ammonia and Alcohol Integration Project in Duolun County, Xilingol League were approved.
The construction site of Guodian Investment Yangtze River Ecological Hydrogen Production and Storage Project in Keerqin Right Wing Front Banner is located in Xing'an League Economic and Technological Development Zone. The construction unit is Guodian Investment Yangtze River Ecological Energy Co., Ltd., with a total investment of 54.5 billion yuan and a planned construction period from 2025/09 to 2027/09.
The construction scale and content include: electrolytic water hydrogen production capacity of 220000Nm ³/h, hydrogen storage capacity of 1.32 million Nm ³ (1.6MPa), 54 kilometers of 220kV transmission line from the wind farm to the hydrogen production station, covering an area of 1500 acres.
The construction site of the Green Hydrogen to Ammonia and Alcohol Integrated Project in Duolun County, Xilingol League, Inner Mongolia is located in the Economic Development Zone of Duolun County, Xilingol League. The construction unit is Inner Mongolia Geleng Nuojin Hydrogen Energy Technology Co., Ltd., with a total investment of 10.9 million yuan and a planned construction period from November 2024 to November 2026.
Construction scale and content: The main construction content is a 130000 ton/year hydrogen production line, equipped with electrolytic cell equipment, with a total hydrogen production capacity of about 460000 Nm ³/h. It uses green hydrogen to produce 500000 tons/year of synthetic ammonia and 300000 tons/year of methanol. The total construction area is approximately 740000 square meters. The project will be constructed in stages, with the first phase consisting of an annual output of 60000 tons of green hydrogen, an annual output of 300000 tons of synthetic ammonia, and hydrogen fuel cells (used for peak shaving and arranged in the electrolytic water hydrogen production section), including supporting facilities such as a comprehensive office building, electrolytic water hydrogen production workshop, green ammonia production workshop, biomass gasification plant, gas storage tank, plant wide torch, substation, purification station, circulating water station, sewage treatment station, comprehensive warehouse, comprehensive maintenance workshop, and chemical warehouse; The second phase of construction includes an annual output of 70000 tons of green hydrogen, 200000 tons of synthetic ammonia, 300000 tons of methanol, and hydrogen fuel cells (used for peak shaving and arranged in the electrolytic water hydrogen production section), including supporting facilities such as electrolytic water hydrogen production workshop, green methanol production workshop, green ammonia production workshop, and gas storage tanks.
Air Separation Plant/Nitrous oxide plant/CO2 recovery plant/Hydrogen plant/Acetylene Plant/Mobile Tank/ISO Tank Container/Cryogenic Storage Tank/LPG Storage Tank/Cryogenic Pump/Micro Bulk Tank Solutions/Cryogenic Semi Trailer Transport Tanker/LPG Semi Trailer Tanker/Dewar Flask/Vaporizer/Cylinders/Dry ice making machine/Calcium Carbide